operations since SunEdison was no longer an affiliate of the Company.
    
Historical Engineering, Procurement and Construction Contracts and Module Warranties

SunEdison served as the prime construction contractor for most of the Company's renewable energy facilities acquired from SunEdison pursuant to engineering, procurement and construction contracts with the Company's project-level subsidiaries. The Company also generally obtained solar module warranties from SunEdison, including workmanship warranties and output guarantees, for those solar facilities that the Company acquired from SunEdison that utilized SunEdison modules. Third party insurance was procured by SunEdison to back-stop payment of warranty claims for SunEdison modules purchased from January of 2011 through January of 2017.

During the first quarter of 2017, the Company received $7.0 million from SunEdison in satisfaction of outstanding claims made under engineering, procurement and construction contracts, of which $4.8 million related to the Company's renewable energy facility located in Chile and compensated the relevant project company as the facility's performance during the warranty period was below that guaranteed by an affiliate of SunEdison under the applicable EPC contract. These receipts were treated as equity contributions from SunEdison within Net SunEdison investment on the consolidated statements of stockholders' equity for the year ended December 31, 2017. As discussed above, pursuant to the Settlement Agreement entered into with SunEdison, and upon the consummation of the Merger with affiliates of Brookfield on October 16, 2017, these construction and related contracts were rejected without further liability, claims or damages on the part of the Company.

Historical Interest Payment Agreement with SunEdison

Since the Company's initial public offering (“IPO”) on July 23, 2014, the Company was a party to an interest payment agreement with SunEdison, pursuant to which SunEdison would pay a portion of the scheduled interest payments on certain corporate-level indebtedness. The Company received equity contributions totaling $8.0 million from SunEdison pursuant to this agreement during the year ended December 31, 2016. The 2016 contribution was received in the first quarter of 2016 and accrued for during fiscal 2015. The Company did not receive any payments from SunEdison pursuant to this agreement subsequent to the first quarter of 2016. As discussed above, pursuant to the Settlement Agreement entered into with SunEdison, and upon the consummation of the Merger with affiliates of Brookfield on October 16, 2017, this agreement was rejected without further liability, claims or damages on the part of the Company.

Historical Support Agreement with SunEdison

The Company entered into a project support agreement with SunEdison (the “SunE Support Agreement”) on July 23, 2014, which provided the Company the option to purchase additional renewable energy facilities from SunEdison and also provided the Company a right of first offer with respect to certain other renewable energy facilities. During the year ended December 31, 2016, the Company acquired renewable energy facilities with a combined nameplate capacity of 19.2 MW from SunEdison under the SunE Support Agreement. The Company did not acquire any renewable energy facilities from SunEdison under the SunE Support Agreement during the year ended December 31, 2017.

As discussed above, pursuant to the Settlement Agreement entered into with SunEdison, and upon the consummation of the Merger with affiliates of Brookfield on October 16, 2017, the SunE Support Agreement was rejected without further liability, claims or damages on the part of the Company.

The Company continues to maintain a call right over 500 MW (net) of operating wind power plants that are owned by a warehouse vehicle that was owned and arranged by SunEdison (the “AP Warehouse”). SunEdison sold its equity interest in the AP Warehouse to an unaffiliated third party in 2017.

Insurance Allocation Agreements

     The Company, TerraForm Global, SunEdison and certain of their respective directors and officers shared $150.0 million of directors’ and officers’ liability insurance policies that covered the period from July 15, 2015 to July 14, 2016 (the “D&O Insurance”). SunEdison and the independent directors of SunEdison entered into an agreement, dated March 27, 2017 and amended on June 7, 2017, with the Company, TerraForm Global, their respective current directors (as of that date) and certain of their respective current officers (as of that date) (the “YieldCo D&O Parties”) related to the D&O Insurance, which included, among other things, an agreement by SunEdison to consent to proposed settlements of up to $32.0 million to be